BOM Creation, Version and Effective-date Control
Maintain parent item, components, scrap, substitutes and effective dates correctly.
Learning objective
Create a controlled BOM usable by planning, production and costing.
03
Steps
01Confirm parent item, production organisation, UOM and BOM purpose.
02Enter component quantity, scrap, issue method and operation position.
03Configure substitutes, co/by-products and lot-size rules.
04Use versions and effective dates for engineering changes; do not overwrite history.
05Run completeness checks, approve, release and validate the MRP explosion.
- 01
Confirm parent item, production organisation, UOM and BOM purpose.
- 02
Enter component quantity, scrap, issue method and operation position.
- 03
Configure substitutes, co/by-products and lot-size rules.
- 04
Use versions and effective dates for engineering changes; do not overwrite history.
- 05
Run completeness checks, approve, release and validate the MRP explosion.
04
Implementation notes
- BOM UOM conversion must align with inventory and production.
- Keep the reason and approval trail for engineering changes.
- Document differences between costing and production BOMs.