U9 cloud Capacity: Load Trial and Bottleneck Review
Use work-centre calendars, efficiency and operation demand to calculate load and approve capacity responses.
Learning objective
Identify a bottleneck in one planning horizon and verify load before and after adjustment.
Roles
Planning, production, maintenance, costing, HR and IT
Prerequisites
- Trusted work-centre and routing times.
- Maintained production and downtime calendars.
Completion checks
- Overload traces to specific order operations.
- Adjusted load and dates meet approved targets.
Common errors
- Treating nominal hours as available capacity.
- Changing efficiency to hide problems.
Thailand project note
For Thailand, confirm Thai/English masters, THB and foreign currencies, Asia/Bangkok time, segregation of duties and local record retention. VAT, WHT, customs, BOI, statutory accounting, product compliance and occupational-safety settings require current review by qualified Thai professionals; this is not legal or tax advice.
Steps
- 01
Govern work centres, shifts, calendars, available hours, efficiency and downtime.
- 02
Confirm routing, standard time, lot size and planned-order cut-off.
- 03
Calculate required load and available capacity by day or week; retain parameters.
- 04
Review overloaded and underloaded centres and trace them to orders and operations.
- 05
Evaluate overtime, changeover, alternate resource, subcontracting or date changes.
- 06
Obtain production, planning, maintenance and costing approval, then recalculate.
- 07
Compare actual hours and output with plan; correct data instead of hiding variance.
Implementation notes
- Focus first on constraint resources.
- Calibrate efficiency with actual evidence.