U9 cloud Production: Release, Issue, Report and Complete a Work Order

Turn a planning proposal into a controlled work order connecting material, operations, reporting, completion and exception recovery.

生产订单 / Production Order20 minUpdated 2026-08-21
01

Learning objective

Complete one production order from release to finished-goods receipt with reconciled quantity and status.

Roles

Planning, production, warehouse, quality, costing and IT

Prerequisites

  • Effective BOM, routing, work centre and material status.
  • Defined release, change and closure authority.

Completion checks

  • Order input, output, scrap and inventory movements balance.
  • Every key status change retains person, time and source evidence.

Common errors

  • Releasing despite shortages without approved risk treatment.
  • Closing with unresolved returns or production reports.

Thailand project note

For Thailand, confirm Thai/English business and item masters, THB and foreign currencies, Asia/Bangkok time, segregation of duties, electronic records and local document retention. VAT, WHT, customs, BOI, statutory accounting, product compliance and occupational-safety settings require current review by qualified Thai professionals; this tutorial is not legal or tax advice.

03

Steps

01Confirm item, quantity, BOM version, routing, plant, dates and cost object.
02Check capacity and material readiness; shortages or overload require an approved response.
03Approve and release by role, freezing key baselines; version quantity and date changes.
04Issue by order and operation, recording lot, serial, substitutes, returns and scrap reasons.
05Capture start, finish, good, reject, labour and equipment data; do not manage exceptions only on paper.
06Before receipt, reconcile inspection status, quantity balance and open operations; prohibit premature closure.
07At close, reconcile input, output, scrap, unused material, WIP and cost variance; close open exceptions.
  1. 01

    Confirm item, quantity, BOM version, routing, plant, dates and cost object.

  2. 02

    Check capacity and material readiness; shortages or overload require an approved response.

  3. 03

    Approve and release by role, freezing key baselines; version quantity and date changes.

  4. 04

    Issue by order and operation, recording lot, serial, substitutes, returns and scrap reasons.

  5. 05

    Capture start, finish, good, reject, labour and equipment data; do not manage exceptions only on paper.

  6. 06

    Before receipt, reconcile inspection status, quantity balance and open operations; prohibit premature closure.

  7. 07

    At close, reconcile input, output, scrap, unused material, WIP and cost variance; close open exceptions.

04

Implementation notes

  • Test normal, shortage, rework and reversal scenarios.
  • Do not share accounts for critical reporting.
05

References