U9 cloud Project Budget: Freeze Baseline and Control Changes

Manage project-budget changes with versions, effective dates and impact analysis rather than overwriting overruns.

项目预算基线变更 / Project Budget Baseline18 minUpdated 2026-08-21
01

Learning objective

Create evidence across submission, approval, baseline freeze, change and tracking.

Roles

Finance, process owners, key users, IT, consultants and internal audit

Prerequisites

  • Confirm entity, period, currency, masters and access.
  • Prepare approved normal and exception data.
  • Define approvals, cut-off and change control.

Completion checks

  • Results trace to source and accountable role.
  • Quantity, amount, period and status are reviewable.
  • Exceptions retain cause, approval, action and closure evidence.

Common errors

  • Overwriting history and losing traceability.
  • No segregation of duties.
  • Testing only normal flow.

Thailand project note

Thai implementations should confirm Thai/English masters, THB and foreign currencies, Asia/Bangkok time, segregation, approvals and local retention. This covers ERP management controls only; VAT, WHT, BOI, customs and statutory-accounting conclusions require qualified Thai professional review.

Related modules

finance-governancemanagement-accountinginternal-control

03

Steps

01Define project, phase, task, cost account, currency and owners.
02Load approved budget and freeze baseline version and effective date.
03Every change records reason, scope, amount, funding source and expected effect.
04Compare budget, commitment, actual and estimate at completion before and after change.
05Trigger project, finance and management approval by amount and impact.
06Publish a new version while retaining prior baselines and report differences regularly.
  1. 01

    Define project, phase, task, cost account, currency and owners.

  2. 02

    Load approved budget and freeze baseline version and effective date.

  3. 03

    Every change records reason, scope, amount, funding source and expected effect.

  4. 04

    Compare budget, commitment, actual and estimate at completion before and after change.

  5. 05

    Trigger project, finance and management approval by amount and impact.

  6. 06

    Publish a new version while retaining prior baselines and report differences regularly.

04

Implementation notes

  • Pilot one entity and representative period.
  • Exceptions require source, owner and closure evidence.
  • Menus and fields depend on current release and blueprint.