U9 cloud Replenishment: Reorder Point and Safety Stock Review

Set and continually review replenishment parameters using demand variation, lead time, service target and exception monitoring.

补货参数 / Replenishment Parameters18 minUpdated 2026-08-21
01

Learning objective

Create explainable parameters for one item family and validate them with history and scenarios.

Roles

Planning, purchasing, warehouse, sales and finance

Prerequisites

  • Usable demand and lead-time history.
  • Separated MRP and reorder-point scope.

Completion checks

  • Every parameter traces to inputs and approval.
  • Simulation avoids duplicates and meets the target.

Common errors

  • Using one safety-stock day rule for every item.
  • Replenishing twice through MRP and reorder point.

Thailand project note

For Thailand, confirm Thai/English masters, THB and foreign currencies, Asia/Bangkok time, segregation of duties and local record retention. VAT, WHT, customs, BOI, statutory accounting, product compliance and occupational-safety settings require current review by qualified Thai professionals; this is not legal or tax advice.

03

Steps

01Select suitable replenishment items and clean demand, shortage, lead-time and exception history.
02Set service target, review cycle, lot size and sourcing policy.
03Calculate reorder point and safety stock while recording inputs, assumptions, date and owner.
04Simulate higher demand, lead-time delay, inbound supply and current stock in test.
05Review proposed quantity and date, avoiding duplicate supply with MRP.
06Monitor shortage, slow-moving, expedite and forecast-error outcomes.
07Approve parameter changes, retain old values and set the next review date.
  1. 01

    Select suitable replenishment items and clean demand, shortage, lead-time and exception history.

  2. 02

    Set service target, review cycle, lot size and sourcing policy.

  3. 03

    Calculate reorder point and safety stock while recording inputs, assumptions, date and owner.

  4. 04

    Simulate higher demand, lead-time delay, inbound supply and current stock in test.

  5. 05

    Review proposed quantity and date, avoiding duplicate supply with MRP.

  6. 06

    Monitor shortage, slow-moving, expedite and forecast-error outcomes.

  7. 07

    Approve parameter changes, retain old values and set the next review date.

04

Implementation notes

  • Use reorder point only for appropriate items.
  • Safety stock is not permanently frozen stock.