U9 cloud Rolling Budget: Update Forecast with Actuals and Drivers

Retain the approved baseline and update future outlook using volume, price, usage and workforce drivers.

滚动预算预测 / Rolling Budget Forecast18 minUpdated 2026-08-21
01

Learning objective

Create a rolling process that preserves history and explains forecast movement.

Roles

Finance, process owners, key users, IT, consultants and internal audit

Prerequisites

  • Confirm entities, periods, currencies, masters and access.
  • Prepare approved normal and exception test data.
  • Define cut-off, interfaces, approvals and changes.

Completion checks

  • Results trace to source document and accountable role.
  • Quantity, amount, currency, period and status reconcile.
  • Exceptions retain cause, action, owner and closure evidence.

Common errors

  • Masking source errors with manual adjustment.
  • Not freezing versions, making results irreproducible.
  • Testing only normal flow.

Thailand project note

Thai implementations should confirm Thai/English masters, THB and foreign currencies, Asia/Bangkok time, segregation of duties, approvals and local retention. This covers ERP process controls only; VAT, WHT, BOI, customs and statutory-accounting conclusions require qualified Thai professional review.

Related modules

finance-controlmanagement-accountingbusiness-reconciliation

03

Steps

01Freeze annual baseline with organisation, period, currency and approval version.
02Select verifiable drivers for volume, price, material usage, workforce and expense.
03Load actuals and separate true variance, timing and one-off items.
04At a fixed cadence, add future months without overwriting approved history.
05Use driver bridges to explain change from prior forecast.
06After management approval, publish a new version with actions, owners and review dates.
  1. 01

    Freeze annual baseline with organisation, period, currency and approval version.

  2. 02

    Select verifiable drivers for volume, price, material usage, workforce and expense.

  3. 03

    Load actuals and separate true variance, timing and one-off items.

  4. 04

    At a fixed cadence, add future months without overwriting approved history.

  5. 05

    Use driver bridges to explain change from prior forecast.

  6. 06

    After management approval, publish a new version with actions, owners and review dates.

04

Implementation notes

  • Pilot one organisation and representative period.
  • Exceptions need source, owner, approval and closure evidence.
  • Menus and fields depend on current release and blueprint.